Report
Test and Evaluation Trends and Costs for Aircraft and Guided Weapons
Nov 22, 2004
Focus on Testing and Evaluation
Format | File Size | Notes |
---|---|---|
PDF file | 0.1 MB | Use Adobe Acrobat Reader version 10 or higher for the best experience. |
Testing and evaluation (T&E) is a key step in the development of military weapon systems. It is the primary means of ensuring that the system will actually perform its intended function in its intended environment. T&E is an involved and often lengthy process, accounting on average for 21 percent of development costs for fixed-wing aircraft and 15 percent for guided weapons.
Advocates of acquisition streamlining have questioned the scope, duration, cost, and organizational responsibilities of the traditional T&E process. These questions are especially urgent because most T&E expenditures occur later in development, when cost overruns and schedule slips from other activities are more apparent. Some program managers have suggested streamlining measures such as relying on modeling and simulation to dramatically reduce the amount of "open air" testing, combining contractor and government testing, and applying total system performance responsibility (TSPR) contracting to shift certain responsibilities to the contractor rather than the government. In estimating the cost of future acquisitions, decisionmakers need to know whether such measures can in fact achieve their projected savings.
RAND Project AIR FORCE (PAF) studied T&E costs for recent Air Force and Navy fixed-wing aircraft, tactical missile, and guided munition systems to identify trends that might affect such costs in the future. Researchers found that although streamlining initiatives may have reduced the cost of individual tests, the proportion of development costs dedicated to T&E has remained relatively constant. Specific findings include the following:
To further improve their estimates of T&E costs, analysts should have a fuller understanding of what the government actually spends on testing. It is currently more difficult to collect and analyze cost data from government organizations than it is from contractors. Consistent accumulation and reporting of such costs (to standards similar to those for contractor data) would greatly improve the accuracy of future cost estimates and provide government personnel better information for planning and management.
This research brief describes work done for RAND Project AIR FORCE.
This report is part of the RAND Corporation Research brief series. RAND research briefs present policy-oriented summaries of individual published, peer-reviewed documents or of a body of published work.
This document and trademark(s) contained herein are protected by law. This representation of RAND intellectual property is provided for noncommercial use only. Unauthorized posting of this publication online is prohibited; linking directly to this product page is encouraged. Permission is required from RAND to reproduce, or reuse in another form, any of its research documents for commercial purposes. For information on reprint and reuse permissions, please visit www.rand.org/pubs/permissions.
The RAND Corporation is a nonprofit institution that helps improve policy and decisionmaking through research and analysis. RAND's publications do not necessarily reflect the opinions of its research clients and sponsors.