Development of the F-35 Joint Strike Fighter was shared by the United States (for the U.S. Air Force, Navy, and Marine Corps), Australia, Canada, Denmark, Italy, the Netherlands, Norway, Turkey, and the United Kingdom. In 2012, these countries agreed to manage F-35 sustainment assets as a global pool. This report reviews other international military aircraft spares pooling programs from the 1950s to the present to identify lessons learned.
A Review of Selected International Aircraft Spares Pooling Programs
Lessons Learned for F-35 Spares Pooling
Download
Download eBook for Free
Format | File Size | Notes |
---|---|---|
PDF file | 0.4 MB | Use Adobe Acrobat Reader version 10 or higher for the best experience. |
Purchase
Purchase Print Copy
Format | List Price | Price | |
---|---|---|---|
Add to Cart | Paperback54 pages | $17.50 | $14.00 20% Web Discount |
Research Questions
- RAND analysis of the nine-country pool of F-35 Joint Strike Fighter sustainment assets proposed three main areas of potential risk for U.S. Air Force participation: prioritization of scarce spares assets, management of innovators versus laggards, and coping with partners unable or unwilling to pay their fair share. Were these issues present in other historical and contemporary spares pooling programs, and, if so, how were they managed?
- What other lessons can be identified from other military aircraft spares pooling programs to aid in the management of the F-35 Joint Strike Fighter spares pooling program?
The F-35 Joint Strike Fighter is a fifth-generation stealth fighter whose system development was shared by nine countries: the United States (for which the F-35 is being jointly procured by the U.S. Air Force, U.S. Navy, and U.S. Marine Corps), Australia, Canada, Denmark, Italy, the Netherlands, Norway, Turkey, and the United Kingdom. In 2012, these countries agreed that F-35 sustainment assets would be managed as a single global pool, which would be centrally managed by the F-35 production support manager. In the formal agreement establishing this pool, language was also included to allow participants to opt out of the global pool, should a nation desire to establish (and be willing to pay for) a separate stock of assets. This report reviews other selected historical and current international military aircraft spares pooling programs involving the United States, major European North Atlantic Treaty Organization allies, and other U.S. allies to identify lessons learned. The most successful historical programs were characterized by a single dominant partner that could establish the ground rules and resource allocation priorities, as well as control configuration. At the same time, successful programs made major efforts to ensure fairness, equality, and transparency for all partners, based on relative contribution and need.
Key Findings
Lessons Learned from Historical International Spares Pooling Initiatives
- The negotiation of international spares pooling programs for common major weapon systems has been attempted many times since the 1960s, but they have proven to be very difficult to implement.
- Major barriers include (1) security of supply and prioritization of scarce spares assets and (2) configuration management and management of innovators versus laggards. These two challenges can be difficult to overcome unless one partner plays a dominant role in the pooling arrangements.
- Conflicting industrial, technological, and economic interests and objectives were a major challenge, especially for all-European programs or programs in which all the partners were roughly of equivalent size and influence.
- The most successful programs were characterized by a single dominant partner that could establish the ground rules and resource allocation priorities, as well as control aircraft configuration. At the same time, successful programs made major efforts to ensure fairness, equality, and transparency for all partners, based on relative contribution and need.
Policy Measures That Facilitate Spares Pooling
- Successful programs have mitigated the problem of U.S. export control laws and regulations by retaining U.S. ownership of all spares except when they are installed in ally-owned aircraft.
- All aircraft should conform to U.S. configuration standards, with the proviso that the U.S. Air Force pays for the nonrecurring costs of upgrading the aircraft.
- Incentives for the prime contractor to meet international fleetwide performance metrics and priorities require a splitting out of the smaller foreign fleets with separately calculated metrics so that these fleets are serviced with the same priority as the larger U.S. fleet.
Table of Contents
Chapter One
Introduction and Overview
Chapter Two
NATO and European Experience with International Spares Pooling
Chapter Three
The C-17 Global Integrated Sustainment Partnership
Chapter Four
Conclusions
Research conducted by
This research was conducted within the Resource Management Program within RAND Project AIR FORCE.
This report is part of the RAND Corporation Research report series. RAND reports present research findings and objective analysis that address the challenges facing the public and private sectors. All RAND reports undergo rigorous peer review to ensure high standards for research quality and objectivity.
This document and trademark(s) contained herein are protected by law. This representation of RAND intellectual property is provided for noncommercial use only. Unauthorized posting of this publication online is prohibited; linking directly to this product page is encouraged. Permission is required from RAND to reproduce, or reuse in another form, any of its research documents for commercial purposes. For information on reprint and reuse permissions, please visit www.rand.org/pubs/permissions.
The RAND Corporation is a nonprofit institution that helps improve policy and decisionmaking through research and analysis. RAND's publications do not necessarily reflect the opinions of its research clients and sponsors.